The Suncoast Parkway 2 is a four-lane toll facility that extends the existing Suncoast Parkway northward for 13 miles from US 98 to SR 44 in Lecanto. The project includes:

  • Constructing full interchanges at US 98 and W. Cardinal Street and a partial interchange at SR 44
  • One wildlife corridor and three wildlife culverts
  • 15 new bridges
  • Two all-electronic tolling gantries and equipment buildings
  • Related drainage, lighting, highway signing, traffic signalization, guardrail and sidewalk
  • The Suncoast Trail, part of Florida's Statewide Greenways and Trails System, will be extended to SR 44 and a pedestrian overpass constructed over US 98
Florida’s Turnpike Enterprise is constructing the Suncoast Parkway 2. The cost for this project is approximately $134 million. Work began in February 2018 and is expected to be completed in 2022. Funding is entirely based on Turnpike toll and concessions revenue.

Aerial Displays
Suncoast 2 Map
Interchange – US 98
Interchange – Cardinal Street
Interchange – SR 44
Section 1 - US 98 to Withlacoochee State Forest
Section 2 - W. Oak Park Blvd. to W. Cardinal St.
Section 3 – Mockingbird St. to W. Grover Cleveland Blvd.
Section 4 – Homosassa Trail to SR 44
Typical Section


For information about this project, contact Katie Mitzner, Construction Community Outreach Specialist, 407-264-3069 or via e-mail at: Katie.Mitzner@dot.state.fl.us.

Public Information Meeting
Postponed


(Click box for additional meeting information)

The Suncoast Parkway 2 Phase 2 will be a four-lane (two lanes in each direction) toll facility that extends from SR 44 to CR 486, a distance of approximately three miles. The project will evaluate the following:

  • Completing the interchange at SR 44 to accommodate northbound traffic movements. Construction for southbound traffic movements is currently underway as part of the Suncoast Parkway 2 from US 98 to SR 44.
  • An at-grade intersection at CR 486
  • One SR 589 mainline, All Electronic Tolling (AET) location
  • Related drainage, lighting, highway signing, traffic signalization, guardrail, and sidewalk.
  • The continuation of the Suncoast Trail, part of Florida’s Statewide Greenways and Trails System.

For information about this project, contact Stephanie Eisenberg, Community Outreach Specialist, 407-264-3064 or via e-mail at: Stephanie.Eisenberg@dot.state.fl.us.

Mailing List

Join our Mailing List
You can add your name to the project mailing list by filling out the form below.




Send a Comment