Lessons Learned - Roadway *
* All links require Adobe Reader. To download, click the
icon.
04/28/04 Resurfacing Projects
with Guardrail
12/14/04
Water table
in close proximity to temporary pavement
12/14/04
Conflicts with underground structures/utilities
12/14/04
Permit not
included in bid documents
12/20/06 Attenuators
for temporary toll booths
12/20/06
Dredging included in general excavation quantities
12/20/06
Existing riprap was not shown on plans
12/20/06
Incorrect callout of right-of-way corner
12/20/06
Use of outdated right-of-way maps to prepare plans
12/20/06
Guardrail
attenuator not in compliance with Standard Index
12/20/06
Removal of
thermoplastic striping
12/20/06
Right-of-way shown
and labeled twice along ramp
05/21/07 Cross-check
of required pay items during quality control review
05/21/07
Area for retention pond not included
08/15/07
Shoulder ponding in bottom of vertical curve on roadway
08/15/07
Locating landfills in construction plans
08/15/07
Railroad coordination
11/16/07 Dowelled Transverse Concrete Construction Joint
12/06/07 Subgrade/Subdrainage Beneath Gantry Concrete Pavement
03/06/08 Reference Points
03/06/08 RFI Process
01/23/09
Plan Note Inconsistent with Lane Closure Analysis and Turnpike's Lane Closure Policy
01/23/09 Removal of Extra-Depth Asphalt in Area of Full-Depth Reconstruction
01/23/09 Pay Item for Special Guardrail Posts not in Summary of Pay Items
01/23/09 TCP and Transition to Existing Lanes
08/26/09
Soundwall Conflict
04/08/10
Toll Plaza TCP
10/18/10
Median U-turn
|